"To the Chief of the BTU, Military Engineer 1st Grade, comrade Korobov
Following decrees issued by the Government, the Kirov factory is building a series of experimental vehicles without having any contracts for them. Letter #6109 sent on November 15th, 1940, asked you to send these contracts. Letter #2239/s sent on February 20th, 1941, repeated the request. Nevertheless, we have not received any contracts from you.
I am sending you a report of the approximate cost of experimental works performed by the Kirov factory in 1941 regarding Objects ##150, 220, 221, 212, and KV-3, for the sum of 5,350,000 rubles in total. Please send us the information to issue bills regarding these projects.
As for the signing of contracts regarding the projects, we ask you once more to accelerate their composition.
Deputy director, Zherekhov.
...
Report on the estimated cost of experimental work at the Kirov factory in 1941 (in thousands of rubles)
Lantsberg
May 30th, 1941"
CAMD RF 38-11355-101
Following decrees issued by the Government, the Kirov factory is building a series of experimental vehicles without having any contracts for them. Letter #6109 sent on November 15th, 1940, asked you to send these contracts. Letter #2239/s sent on February 20th, 1941, repeated the request. Nevertheless, we have not received any contracts from you.
I am sending you a report of the approximate cost of experimental works performed by the Kirov factory in 1941 regarding Objects ##150, 220, 221, 212, and KV-3, for the sum of 5,350,000 rubles in total. Please send us the information to issue bills regarding these projects.
As for the signing of contracts regarding the projects, we ask you once more to accelerate their composition.
Deputy director, Zherekhov.
...
Report on the estimated cost of experimental work at the Kirov factory in 1941 (in thousands of rubles)
Stage | ## | 150 | 220 | 221 | 212 | 218 | KV-3 | KV-4 | KV-5 |
Draft and technical projects | 50 | 100 | 50 | 100 | 75 | 100 | 120 | 120 | |
Models | - | 25 | - | 25 | 25 | 50 | 50 | 50 | |
Working blueprints | 50 | 250 | 125 | 300 | 125 | 350 | 330 | 380 | |
Prototype assembly and factory trials | 1 | 900 | 1200 | 1200 | 1100 | 900 | 1300 | 1800 | 2200 |
2 | - | 1200 | - | - | - | - | - | - | |
Proving grounds trials | 1 | 100 | 125 | 125 | 100 | 75 | 150 | 150 | 150 |
2 | - | 125 | - | - | - | - | - | - | |
Correction of blueprints after trials | 25 | 75 | 50 | 75 | 25 | 100 | 100 | 100 | |
Repair of prototypes and modifications | 1 | 375 | 450 | 450 | 300 | 275 | 450 | 550 | 600 |
2 | - | 450 | - | - | - | - | - | - | |
Total | 1500 | 4000 | 2000 | 2000 | 1500 | 2500 | 3100 | 3600 |
Lantsberg
May 30th, 1941"
CAMD RF 38-11355-101